Introduction
The idea of an interpretive center at Sea
Ranch has been around for a long time. The Sea Ranch Comprehensive
Environmental Plan (CEP) uses the terms “library,” “repository,” and “space
within its community facilities” to describe a physical place where members
and, perhaps, prospective members could go for information on The Sea Ranch
design philosophy, development history, landscape design, plants and
wildlife. The underlying idea is that if members and prospective owners
truly understand the special qualities of TSR natural environment and the
reasons for the design philosophy, they will act to protect them. CEP goals
and guidelines pertinent to the idea of an interpretive center are listed in
Appendix A.
On June 21, 2002, the TSRA Board authorized Chairperson
Ann Harriman to establish a task force to explore the idea of an
interpretive center for The Sea Ranch.
The Board charged the task force to study:
- What purposes or objectives an Interpretive Center
(IC) might accomplish?
- Who might make use of the IC, e.g., members,
potential members, architects, builders, scholars?
- What content should be included?
- Explore alternative options.
The ICTF held six meetings between July 2002 and
February 2003. At the beginning, the task force decided that “interpretive
center” would be broadly interpreted to include a wide range of ways to
communicate information about design and the environment at The Sea Ranch.
Also, from the beginning, discussion centered on how to convey TSR design
concepts to a variety of audiences including prospective owners, members
considering additions to their houses, realtors, architects and designers,
and contractors.
The task force recognizes that all Sea Ranchers need to
know about the Sea Ranch environment—its history, the processes shaping it
and the plants and wildlife inhabiting it. The task force believes that
effective use of the website, publications and space in existing community
facilities can enhance understanding for all of us.
Lack of knowledge of the environment is manifested
primarily as inappropriate house and landscaping designs. In addition, with
new staffing for design review and two new members on the Design Committee
(DC), the time seemed right to explore in detail how people get and use
information about design at TSR. Thus, the task force limited its
deliberations to design issues.
Work Program
The task force began by developing a work
program to guide its efforts. The program lists 5 tasks:
- Identify problems and needs.
- Document problems and needs.
- Identify options for addressing problems and needs.
- Conduct or participate in a workshop or Forum.
- Prepare recommendations and report.
The sections below describe the results of work on
these tasks. Appendix B to this report contains the entire work program.
Identify Problems and Needs
The task force identified ten
problems or needs to be confirmed and/or addressed:
1.
The DC receives some plans for houses that are inappropriate for Sea
Ranch. By the time the plans are submitted, the owners have already
invested significant time and money and it is difficult to turn them down.
Some architects, designers, builders and contractors fail to comply with TSR
design requirements.
2.
Realtors are in the business of selling lots and houses and some do
not explain to prospective buyers the responsibilities of owning property at
TSR.
3.
Space in the TSR office is cramped for both offices and storage.
4.
Visiting architects, landscape architects and scholars have no place
to meet where they can review materials about the history and development of
TSR.
5.
Current periodicals and other publications may fail to communicate
properly to various audiences.
6.
Existing owners need continuing education especially as remodeling
and additions become more frequent.
7.
TSRA fails to differentiate between TSR and other high-end real
estate developments.
8.
Vacation renters and casual visitors have no way of learning about
The Sea Ranch “concept” and what that means in terms of how we treat our
environment.
9.
Owners need to learn how to choose and interact with architects and
others involved in the design process.
10.
Non-compliance with landscape guidelines can change the character of
TSR environment.
Document Problems and
Needs/Identify Options
Task force members reviewed available literature explaining Sea Ranch to
prospective or new owners, interviewed several realtors and architects,
talked with TSRA staff about space needs at the office and surveyed owners
about their experiences with design review. The results of these efforts
are summarized below.Review of information available to prospective buyers
The task force reviewed both
historic and current literature explaining Sea Ranch. Oceanic California,
Inc. prepared several attractive and interesting publications to explain and
promote Sea Ranch. Since the Association took control, no publication of
comparable quality has been created to explain the natural environment and
design philosophy shared by Sea Ranchers. The Sea Ranch is no longer a real
estate development, but a community. The need now is not for promotional
literature, but for material to inform prospective and new members about the
Sea Ranch design philosophy and the responsibility shared by all members to
protect the special environmental qualities of TSR as they build in and
enjoy the community.
Interviews with Realtors
Task force members interviewed 5 of the
75 or so realtors who sell property at TSR about problems with information
about design at TSR and suggestions for solutions. Dibby Tyler interviewed
Edie Baker, Debbie Rosson and Hanne Liisberg of Coldwell Banker and June
Way-Dresher of Rams Head Realty. Gene Weston interviewed Richard Thomure of
Sea Ranch Properties. Copies of the interview summaries are included in
Appendix C to this report.
Problems noted include:
- Clients sometimes spend less time at Sea Ranch
before deciding to buy than they did in the old days.
- Increasing numbers of clients are using the web to
screen properties.
- Buyers get plenty of information, especially at
closing, but may not read it.
- The number of agents has grown rapidly in this boom
market and many are not as familiar with Sea Ranch as the “old timers.”
- People do not have “standing” to get information
about lots from the Association until after they buy property. Realtors
cannot (and should not) answer specific questions about what the
Association would permit on a given lot.
- Clients experience inconsistency with design review
decisions. The process is not clear.
- In the early days, realtors had promotional packets
with lots of graphic materials including the design manual. Prospects
were given tours of The Sea Ranch. The concept was sold—not just lots.
Now realtors give out a brochure and map and most do not conduct a tour.
- The space used by the Design Department and Design
Committee is poor and gives a bad impression.
Suggestions include:
- Several realtors routinely refer clients to the TSRA
website for information. It would be good to have a section specifically
for prospective buyers including illustrations of good design.
- Some of the information distributed at the time of
the site visit might be provided earlier in the process.
- A center would be good—someplace with visuals to
clearly explain why “less is more.”
- Organize Sea Ranch “old timers” to help answer
questions from prospective and new owners.
- The Association could hold a periodic meeting for
realtors to give them up-to-date information about design review (and
other issues) so the realtors can give accurate information to their
clients
- When important changes occur, like the appointment
of Dick Whitaker, an email announcement could be sent to realtors via the
multiple listing service.
- Clients need and want more information about the Sea
Ranch concept and design review. The new design manual should contain
more graphs and visuals.
- Rent Obie Bowman’s old office for the Design
Committee and the upstairs of the old Henley Gallery for an interpretive
center.
Interviews with Architects
Dibby Tyler interviewed Fiona O’Neill and Don Kemp interviewed Ralph
Matheson about their experiences with design review. Copies of the
interview summaries are included in Appendix C to this report.
Suggestions include:
- People need more discussion, earlier in the process,
about design possibilities and constraints of their particular lots.
- Letters to applicants from the DC should be clear,
tactfully worded, and state the reasons for decisions.
- Dick Whitaker should be authorized to permit small
changes in design.
- Owners need clearer guidelines and more information
about designing “infill” projects.
- Clients expect that design issues can be
negotiated. If that is not the case, then this needs to be communicated
to applicants and their designers.
- Design criteria and changes in emphasis by the DC
need to be clearly conveyed to the local design community. The design
manual should include a clear discussion of house size.
- The DC should consider opening meetings to
architects and designers when their projects are being reviewed.
- Periodic meetings of the DC and staff with the
design community would be helpful.
Talks with TSRA staff
The task force discussed space needs
with TSRA staff. Additional space is needed for Dick Whitaker and another
architect that will be hired soon. Community Manager Jim Carruthers is
planning to add space to the upstairs. Dick Whitaker is drawing plans to
modify the entrance to the building and provide downstairs space for the DC
to meet. The remodel will include space for displays illustrating good
design at TSR.Telephone survey of owners
The task force developed a questionnaire
and Matt Adams, Don Kemp, Jackie Knowles, Laurie Mueller and Dibby Tyler
conducted a telephone survey of owners about their experiences with design
review. A copy of the questionnaire with a tabulation of the responses is
included as Appendix D to this report.
The sample included 50 Sea Ranch owners: 40 of the 64
owners who received building permits for new houses in 2000 and 2001 and 10
of the 50 owners who received building permits for additions in 2000 and
2001. Of the 50, 39 (78%) were interviewed—30 who built new houses and 9
who added to existing houses. Fifteen of the respondents are full time Sea
Ranchers, 18 use their homes part time and 5 had houses still under
construction. About 64% had been long-time renters before they bought at
Sea Ranch and about 74% had spent more than a month at Sea Ranch before
buying.
Key results are:
- Realtors were the main source of information about
Sea Ranch for 82% of the respondents before they bought property.
- Architects and designers were the main source of
information about design review for 77% of the respondents.
- Respondents ranked contacts with TSRA staff (62%),
TSR publications (59%) and the TSRA website (49%) as effective ways to
convey information about design. Videotapes or CDs, meetings, and
displays at a specific TSR site were each considered effective by 33% of
the respondents.
- Thirty-three of the 39 respondents used architects
or designers who had designed other Sea Ranch houses and 37 used local
contractors.
- In almost 75% of the cases, the DC approved original
plans with only minor changes. Five owners had initial plans rejected.
- Only 3 respondents (less than 1%) had a generally
negative response to design review and only 1 was totally negative.
- When asked for positive aspects of design review,
many praised TSRA staff using terms such as fair, accessible,
professional, careful, friendly, responsive, and flexible. The process
was deemed clear, painless, predictable, reasonable, and quick. Four
noted that DC comments resulted in a better house.
- When asked about negative aspects of design review,
different people viewed the same staff as arrogant, inflexible, rude,
dogmatic and inaccessible. Some criticized the process as slow, too
detailed, arbitrary, inconsistent, frustrating, and trendy. Others noted
inadequate reasons given for decisions.
- Suggestions for improvement included:
-
information
on TSR concept and design for realtors and rental agents
-
updated
design manual, organized by topic, with summaries and a flow chart
-
adherence
to The Sea Ranch “concept” and better enforcement
-
notices to
neighbors about resubmitted plans
-
open Design
Committee meetings
-
changes in
standards especially regarding new materials and eaves
-
better
information about landscaping and tree removal.
Participate in Forum
The task force recognized the importance of
considering the views of all interested Sea Ranchers in the study. All
meetings were open and listed in the Bulletin and minutes of the early
meetings appeared on TSRA website. Two articles about the task force
appeared in the Bulletin and the results of the survey were presented at the
Forum on Design Review on December 1, 2002.
The task force prepared a brief questionnaire handed
out to forum attendees to give them a chance to contribute their views about
design review at TSR. The questionnaire asked for the most positive and
negative aspects of their experience and suggestions for improvement in the
design review process. Twelve questionnaires were turned in at the end of
the meeting and the results paralleled those of the telephone survey. All
reported an essentially problem-free experience with design review. Several
mentioned that their architect or designer handled the process. Positive
aspects (other than “no problems”) included:
- Brochures, workshops during pre-planning
- A local architect
- On-site discussions
- Strict, clear CC&Rs and DC Rules
- Consistent communications
Negative aspects included:
- Change in staff during process
- Inconsistency in decisions
- Lack of explanation of DC decisions
- Length of time
- Analysis required to remove trees
Suggestions were:
- Provide better information to prospective and new
owners.
- Provide information to rental agents and realtors
for prospective buyers.
- Conduct workshops for owners before they begin
designing.
- Be consistent in design decisions.
- Consider alternative building materials.
- Update the design manual.
- Do not issue so many variances.
- Explain TSR characteristics that influence design.
- Communicate DC thinking to membership.
- Study landscape architecture principles.
- Notify neighbors of resubmitted plans.
- Withhold occupancy permits from owners who violate
CC&Rs.
Findings
After reviewing all the information gathered, the task
force reached the following findings:
- Most buyers of property at Sea Ranch know about the
community and its design philosophy.
- Before they buy, most people get information about
Sea Ranch primarily from their realtor.
- When planning to build or add on to a house, most
people get information about design review primarily from their architect
or designer.
- Most members have little or no difficulty with
design review. Those few that have problems usually sell their lots and
move on. In this sense, the process succeeds in weeding out those whose
design views are not congruent with TSR concept.
- Many of the difficulties cited with design review
stemmed from staff changes and vacancies. Ted Smith’s retirement more
than two years ago left a gap in staffing that was not filled until
recently.
- More Sea Ranchers are disturbed by what they
perceive as laxness in design review than by the difficulty of going
through the process.
- The greatest unmet need is for more and earlier
contact with staff or knowledgeable people about issues specific to a lot.
- As Sea Ranch approaches build out, the relationship
of each new building to those around it becomes more important.
- TSRA provides little design guidance specifically
for remodels and additions.
- Many design controversies involve landscaping,
especially tree removal. Members need better guidance.
- Members look primarily to traditional ways of
getting information about design review—TSRA staff and the Bulletin and
Soundings.
- The TSRA website was not used much by the survey
respondents, but many thought that as it continues to add content, it will
be a more important medium to inform both prospective buyers and existing
owners about design issues.
- An “interpretive center” as a separate structure
does not appear needed to help resolve issues with design review. The
problems that arise are mostly related to specific site conditions and
with very few exceptions do not stem from a lack of understanding of “the
Sea Ranch concept.” Simpler, less expensive solutions can effectively
resolve the problems.
Recommendations
1.
Create a clear, concise, colorful and visually-exciting booklet to convey
TSR design principles to prospective buyers. Provide copies to realtors for
distribution to clients as a complement to the currently used black and
white pamphlet (1999).
2. Add
a section to the TSRA website for prospective buyers. The text and graphics
could be similar to, or the same as, the booklet.
3. In
remodeling TSRA offices on Annapolis Road:
·
Provide space for visual displays of excellent design at TSR.
If a design awards program is established, consider displaying models and
photos of award winning houses coupled with a brief explanation of why the
design was chosen for an award. Similar visual material should also be
available on TSRA website.
·
Consider improving direct Sea Rancher access to the design
support staff.
- Improve availability of design department staff to
talk with owners and their architects early in the design process in order
to avoid expensive redesigns later.
5.
Convene an annual meeting with realtors to describe any changes in policies,
design criteria or procedures that a prospective buyer should know. The
meeting would also introduce new realtors to Sea Ranch and consider any
issues relevant to the two groups. Appropriate TSRA staff, Board members
and or committee members would participate.
6.
Convene an annual workshop between TSRA Design Committee members and staff
and local architects and designers for a dialog about any changes in design
criteria or shifts in emphasis, procedural problems, use of new materials,
etc.
7.
Hold an annual meeting for contractors to keep them up to date on design and
building issues at TSR and the use of new materials. The meeting also would
introduce new contractors to TSRA procedures. It might be combined with the
meeting for architects and designers.
8.
Establish a program to train and use volunteers as “design docents” to talk
with prospective and existing owners and their architects, designers and
builders about design issues at TSR. The docents could give out general
information and refer complicated problems to staff. Other tasks might
include helping to organize the annual meetings of realtors, architects and
contractors, conducting tours of both prospective buyers and visiting
professionals and students, and assisting with compliance monitoring.
9.
Increase the visibility of the Design Committee by including profiles of
members in the Bulletin, Soundings and TSRA website, inviting them to speak
at Forums, and, perhaps, having occasional open DC meetings.
10.
Update and distribute the design manual. The updated version should
include graphics, a description and flow chart of the review process and
explicit guidance on issues that tend to cause problems such as house size,
use of new materials, paving, garages, etc.
11.
Prepare new manuals for both landscape design and house remodels.
12.
If the Lodge expansion goes forward, help the Lodge to create
appropriate displays at the “interpretive center” now shown on its plans.

APPENDIX A: CEP GOALS AND
GUIDELINES PERTAINING TO AN INTERPRETIVE CENTER
DESIGN ELEMENT
Goal 1.2-1: A proactive informational program to promote and perpetuate
The Sea Ranch Concept and design philosophy, to challenge the membership to
sustain the tradition of environmental design excellence, and to support a
continuing discussion of environmental design at The Sea Ranch.
Guidelines
1.2-1(c): Develop a library which focuses on environmental design and
the history and philosophy of design at TSR, and which is open to the
membership, the design community, and prospective members of the
Association.
1.2-1(d): Develop in cooperation with the Design
committee a package of informational materials that: Details the history of
the approach to environmental design at TSR; expresses the original
principles guiding development at TSR; and, explains the design process and
its benefits to a new owner and the community at large.
NATURAL RESOURCES ELEMENT
Guidelines
3.1-1(g): Promote and communicate to TSRA members and guests: An
awareness of TSR’s natural resource values; the need and rationale for
management of certain resources, the need for protection of other resources;
and consider formation of a committee or expansion of an existing
committee’s charter to promote TSR’s natural resource values.
3.2-1(f): Provide to TSRA members educational materials
on the variety, quality, and protection of TSR’s adjacent ecological and
recreational resources.
CULTURAL AND RECREATIONAL RESOURCES
Guidelines
4-3-1(d): Provide space within its community facilities for continuing
displays of the natural history and cultural history of The Sea Ranch.
4.4-1(d): Provide for owners and potential owners a
repository of information concerning TSR including documents concerning:
its history; philosophy of development, design and use; community
organization and activities ; and natural resources.
4.4-2(b): Foster communication with the regional
community to develop an understanding of the needs and resources of The Sea
Ranch and to promote understanding of the underlying philosophy of TSR
development and design.
INFRASTRUCTURE ELEMENT
Guideline
5.2-1(e): Provide educational materials and programs pertaining to
septic systems to all owners within Zone 2 and to rental agencies managing
properties within Zone 2, and request the Design Committee to include in its
Preliminary Site Visit packet information related to the proper design and
use of septic systems.
PUBLIC HEALTH AND SAFETY ELEMENT
Guidelines
6.1-1(h): Provide TSRA members with a packet of educational materials
which include information on fire dangers, responsible preventative
measures, and evacuation instructions. The information may be included as
part of a comprehensive Disaster Plan packet for TSR.
6.3-1(e): Use TSRA publications and other
communication resources to support the development and update of a TSR
Disaster Plan, and to educate its members about the potential for and
consequences of a major disaster.

APPENDIX B: ICTF WORK PROGRAM,
Revised August 23, 2002
TASK A. State Problems/Needs
11.
The DC receives plans for houses that are inappropriate for Sea
Ranch. By the time the plans are submitted, the owners have already
invested a lot and it is difficult to turn them down. Some architects,
designers, builders and contractors fail to comply with TSR design
requirements.
12.
Realtors are in the business of selling lots and houses and some do
not explain to prospective buyers the responsibilities of owning property at
TSR.
13.
Space in the TSR office is cramped for both offices and storage.
14.
Visiting architects, landscape architects and scholars have no place
to meet where they can review materials about the history and development of
TSR.
15.
Current periodicals and other publications may fail to communicate
properly to the varied audiences involved with design review.
16.
Existing owners need continuing education especially as remodeling
and additions become more frequent.
17.
We fail to differentiate between TSR and other high-end real estate
developments.
18.
Vacation renters and casual visitors have no way of learning about
The Sea Ranch “concept” and what that means in terms of how we treat our
environment.
19.
Owners need to learn how to choose and interact with architects and
others involved in the design process.
20.
Non-compliance with landscape guidelines can change the character of
TSR environment.
Task B. Document Problems/Needs
Stating a problem or need is an essential first step, but only a first
step. The problem then needs to be documented. That means gathering and
assessing information to confirm the existence of a problem or need and its
magnitude. Without information about the problem, we will have difficulty
supporting the need for an interpretive center. For each stated problem or
need, the list below suggests information that we should collect:
1a.
Take a sample period of time, say the year 1999 or 2000, and obtain a list
of applications for new houses submitted during that year. Then, count the
number of applications that were approved with no difficulty or controversy;
the number that required one or more revisions that were completed without
major controversy, the number that gave the DC major problems, and the
number that led to actual lawsuits.
In other words, let’s find
out how prevalent a problem this is.
1b.
Talk with staff and members of the DC to assess the seriousness of the
problem. In other words, we may be talking about a few houses a year, but
the impact on TSR of a few poorly designed houses a year may be great.
1c.
Talk with staff and members of DC and review data from (1a) to identify as
precisely as possible the kinds of design problems that arise, i.e. houses
too big, too high, too bulky, too much fencing, too much lighting, etc. In
some cases, tightening requirements may be needed.
1d. Review the information currently given to buyers at TSR to identify
gaps.
2.
Talk with a selection of realtors about the information about Sea
Ranch they give clients and what improvements are needed.
3.
Talk with staff and, perhaps, an architect to assess the space needs
at the TSR offices. What is the square footage of building? What are
possibilities for expansion on site? What growth in staff is projected?
What use is being made of electronic storage?
4.
Find out how frequently visiting professionals and students come to
Sea Ranch and how they are handled. What are the gaps?
5. Other?
Task C. Identify Options for Addressing Problems/Needs
Once we have gathered information and assessed the needs, we can begin
to identify approaches to meeting the needs. A variety of approaches
could be used to resolve most of the problems and meet most of the needs.
Items 3 and 4 are the only ones that could be fully addressed by a building.
The other two require substantial additional efforts—an interpretive center
would be only a part of a broader educational effort. We will need to come
up with lists of options for solving problems and meeting needs. As a
starting point, I suggest that potential approaches fall into three
categories:
Building
This could be making new use of an existing building, remodeling or
expanding an existing building or constructing a new building. The
purpose would be to create space for educational materials (displays, maps,
photos, written materials, videos, etc.) and programs to address 1 and 2 and
to provide space for 3 and 4.
Procedures
Problems 1 and 2 are a least partly procedural. For example, when
and how and what information is provided to prospective buyers and new
owners; how preliminary concept plans work; “due process” in the review
system, etc.
Written and electronic materials
The problems we are addressing will all require educational materials.
These can be in a variety of forms and delivered in a variety of ways to the
intended audiences.
Task D. Workshop or Forum
Before we decide on recommendations, we
should provide an opportunity for Sea Ranchers to comment on the ideas we
are considering. An interactive workshop would be best, but takes time to
plan and execute. We need to be thinking about possible formats.
Task E. Prepare Recommendations and Report
After reviewing the problems and options and
listening to comments from Sea Ranchers, we will need to frame
recommendations for the Board and write a report documenting our findings
and deliberations.
Tentative Schedule (very ambitious!)
To accomplish the 4 tasks outlined above, the fastest possible schedule
would be something like this:
August 23: Discuss and finalize work
program; reach agreement on statement of problems and needs, assign
information gathering tasks.
October 4: Report Task B results to task
force. Discuss and make additional assignments to complete B and start C.
October 25: Report Task B and C results
to task force. Discuss results and begin to plan workshop.
November 22: Plan workshop
format and content. Discuss options.
January 2003: Workshop
January 24: Discuss and decide on
recommendations. Make assignments for writing sections of the report.
February 28: Review draft sections of
report. Approve final report and recommendations for submittal to the
BOD.
APPENDIX C: INTERVIEWS WITH REALTORS AND ARCHITECTS
Realtor: Richard Thomure, Sea Ranch Properties
Interviewed by Gene Weston, September 24, 2002
I indicated to Rich that the task force was addressing the difficulty the
Design Committee (DC) has communicating with both new and old members when
they are designing new houses or preparing remodeling plans. Many do not
have any idea how the approval process relates to the TSR Concepts created
by the original developers.
He described to me the process the on-ranch realtors had used in
exposing possible new purchasers to the ranch. This consisted of promotional
packages containing information folders, lots of graphic materials, the
Design Manual (DM), and a specific set tour of the ranch designed to sell
TSR as a whole not just a series of lots. Today, the realtors give out (we
hope) the brochure the Association put out a while back, a map and that's
about all. He indicated that sometimes sales are made by people who don't
even get out of their cars to view properties. He also finds some people
who have lived here a while didn't know the Hot Spot exists. Incidentally,
Rich now has to make his own copies the design manual to hand out because
the Association has run out. (Bad image!)
He said originally, the developer sold TSR design
philosophy as a concept. Unfortunately when the developer left, a void
remained as the Association did virtually nothing to further the concept. He
feels this has contributed to a lack of understanding that has grown and
still exists today. Also, he feels that the Association now has to loosen
up its purse strings in order to participate in some positive selling. Each
individual agent, (85 of them), has his own style of selling, as there is no
overall program and relatively little Association positive guidance or
assistance. There is also the appearance that the DC is too busy. With
Ted Smith and Jerry leaving, it is increasingly difficult to get things
done. There is also the problem that applicants assume each DC decision
creates a new precedent for the next applicant to build on. This is item is
covered in the Design Manual but it is either ignored or applicants are
unaware of it.
Rich indicated that 10 years ago, the average client
was primarily interested in the square footage and number of baths. Now he
is now encouraged by the fact that many new buyers are younger, have some
knowledge of the founding of the ranch and greater appreciation of the
architecture. He has potential clients now who are waiting to buy Turnbull,
Lyndon, Moore and Bowman houses as soon as they come on the market. He finds
more people are interested in the "design concept" and want more
information, which he claims, "they would absorb like a sponge". As a sales
tool, he has given out the book Parallel Utopias, but it's no longer
in print.
There has recently been a large increase in lot
purchases because of the high cost of existing houses. The number of houses
and lots for sale now is about equal at 30 each. This has never been the
case before and indicates that, in the near term, a lot more people, will be
designing homes. He hopes the new DM will contain more graphics and be on
TSRA website. He refers people to the website when they are looking for
property.
He felt any Interpretive Center (IC), should
concentrate heavily on graphics and visual aids. He hopes the DC can become
stronger as a voice, showing a more active face to the membership. This
could give it greater support from TSRA members and the BOD. He thinks the
appointment of Dick Whitaker as Director of Design Review is excellent. He
considers Dick very easy to work and communicate with.
Another comment he made (and I've also heard this from
several sources) is that an applicant starting with the DC seems to get
bounced around by not having consistent direction, due to different teams
reviewing their plans at the various steps in the review process. This
should change!
He mentioned that TSRA office space being used by the
DC is very poor both as a space and it's image and that any future IC be
related to the DC office, if at all possible. A short-term suggestion was
to rent the old office of Obie Bowman for the DC and the upstairs of the old
Henley Gallery for the IC, it's a great space. Finally he believes the TSRA
members have to accept spending some money to accomplish the task that lies
ahead. It is difficult to manage all 3800 acres and its attendant problems
on the current $125/month dues. In addition, the current dues structure of
one size fits all is unfair. (He knows this is "heresy")
Realtor: Edie Baker, Coldwell Banker and June Way- Dresher, Rams
Head Realty Interviewed by Dibby Tyler, September 20, 2002
Edy started selling real estate with Rams Head in 1980
and recently moved to Coldwell Banker. She has over 20 years experience
selling lots and homes at Sea Ranch. June is a realtor with Rams Head.
Edy noted that Sea Ranch has changed a lot over this
time. When she started, the north end was not open yet, there were no
sewers, and the houses were simple—designed according to the original
concepts. Most were used as second homes. She sees the approval of the
“Malibu wall” on the north end as the major turning point. Two-story houses
lined up along the bluff were a “shocker.” The sewers allowed bigger
houses and both interiors and exteriors changed.
She estimates that now about 1/3 of the buyers expect
to live here full-time and increasingly these include younger people who are
still working. In the early days, most people who bought at Sea Ranch had
been renters here and had some knowledge of the development and its
philosophy. Increasing numbers of people learn about Sea Ranch real estate
on the web and make decisions based on pretty pictures of the coast and a
quick weekend visit. Rams Head has stopped all magazine and other
advertising because clients find the firm through its website. And clients
are coming from all over the world. They do not spend as much time on site
as they used to and they come to Sea Ranch with little or no sense of its
history.
Prospective buyers get amble information at the time of
escrow, but often don’t read it all and are surprised when they run into
trouble getting building designs approved. Edy refers her clients to the
Sea Ranch website and even prints out parts of it for them to be sure they
have the information. She thinks the TSRA website is wonderful, but would
be more useful if it had a section specifically for prospective buyers.
There is a need for something simple to convey the Sea
Ranch message. People need to understand what it takes to keep the concept
alive. Videos don’t work well. A center would be great. People need
things to do and she would certainly refer clients to a center. She
suggests displays showing award-winning houses at TSR and visuals to explain
why “less is more.”
In her experience, realtors are becoming more
aggressive here. There are lots of new agents without the roots in this
place that the long-time realtors have.
Realtor: Debbie Rosson, Coldwell Banker
Interviewed by Dibby Tyler, October 1, 2002
Debbie has been a realtor for 8 years with South Coast
and then Coldwell Banker. She specializes in Timber Cove properties, but,
like all the Coldwell agents, sells anywhere on the coast, including Sea
Ranch.
She notes that as real estate people, they are trained
to help people to get their own information and especially interpretations
of information. Her job is to be sure the sales process meets all the legal
requirements and her clients understand what they are doing. She would
always tell people what Sea Ranch is like. For example, she asks if they
want a basketball hoop, a camper in front of the house, or to fix car
engines in the driveway. If they say “yes” to any such questions, she tells
them that Sea Ranch is not for them.
Debbie feels that over the last couple of years the
message from the Association has been, “don’t send prospective buyers here
for information.” Yet, she can’t give them answers to the questions they
ask such as: Can I take down this particular tree to make room for a house
or enhance a view? Or will I be able to add a room, a garage or a deck to
this house? Who can help with these questions? Right now there is no
smooth way to get questions answered. Maybe Sea Ranch could get some
old-timers to hold a Q & A session with prospective buyers and newcomers
once a week or so to clear up some questions. It would also be helpful to
have an update session for realtors so they can give accurate information to
their clients. News like the appointment of Dick Whitaker could be emailed
for distribution with the multiple listings which go to all realtors.
Debbie doesn’t refer people to the website, mainly
because she doesn’t sell that much property at Sea Ranch. Lots of clients
are using the web to screen properties. She doesn’t need to refer them.
Realtor: Hanne Liisberg, Coldwell Banker
Interviewed by Dibby Tyler, October 1, 2002
Hanne has been with Coldwell for several years,
recently bought two lots at Sea Ranch and is in the process of getting
approval for a house designed by her husband on one of the lots. Like
others I talked with, she noted that the site visit with Bill Wiemeyer after
escrow closed was very helpful and she wonders if some of the information in
the packet he provides at this point could be available earlier in the
process.
Hanne Liisberg routinely refers clients to the
website. She thinks it is excellent, but it might have a little more on the
design philosophy—perhaps a self-guided tour that people could print out
that illustrates good design. The design review process is not always
clear. One of her clients had a house turned down because it used glass
brick, but they could see other houses with glass brick that had been
approved. She feels that too many exceptions have been granted and it is
hard now to toe the line. Most problems arise with people who buy lots
rather than existing houses.
She wondered if we could put more burden on sellers to
provide information to prospective buyers about such things as trees and
additions. The sellers have standing with TSRA to ask the questions whereas
the buyers do not. There is no good way for them to get information they
need about problems specific to the property they are considering. It would
also be helpful to have periodic information forums for realtors.
Interviewer’s Note: At a general
level, a “center” might help with these problems, but so much of the concern
is specific to an individual property and what might or might not be
allowed. How could a center address that need?
Designer: Ralph Matheson
Interviewed by Don Kemp, November 25, 2002
We discussed the design review process in terms of the
process itself and in terms of the intent of the process. Ralph has brought
many projects through the design review process since he began working up
here in 1967.
The Process
Ralph feels that the biggest issues now
are “in-fill” related. He feels that the owners need to have more guidance
on this. In the past the owners communicated more directly with the Design
Committee and got more of a picture of what could be accomplished on their
parcels. More discussion of these issues earlier in the process, even before
the site visit, would be helpful.
The conceptual meeting no longer takes place with the
committee. Instead, the communications are normally handled via a letter to
the owner. This approach sometimes creates a sense that the DC is
“dictating” as opposed discussing. If this method is to be used, great care
should be taken in the writing of the letters. Stern sounding letters get
the relationship off to an unnecessarily adversarial start.
Another observation is that the process of approving
small changes could be expedited with the delegation of authority to someone
like Dick Whitaker.
The Intent
The intentions of the DC are not clear.
It would be helpful if the guidelines could be made clearer to the owners.
General Comments
Ralph has been through 5 DCs and feels
that composition has been very good. In recruiting future members, the DC
goals should be very much taken into account.
The staff and the site visits are good.
People usually talk to realtors and stop in to talk to
contractors on jobs to get their initial input. They are usually pretty
clear about what they want by the time they walk into an architect’s office.
Ralph generally sits down with them and goes through the design review
process and the guidelines early on in the relationship.
He says his experience has been that most plans are
approved with minor changes.
Some architects will use the DC to “push” the client
when they themselves want to avoid being the bearer of unwanted news.
There is a view among clients that the DC does not
compromise; they mandate. If there is to be no negotiating, then the clients
should enter the process with that expectation. As of now, they feel that
things can be negotiated and are usually “disappointed” to find that they
are unable to do so.
Interviewer’s
Notes: Give more authority to someone, currently Dick Whittaker, to OK
small changes in the interest of time. Review all remaining unbuilt sites
and develop guidelines for design issues specific to those respective sites.
The DC makes the final decisions anyway, so why not do it upfront so the
owners can find out before they get started down a path they will need to
change.
Architect: Fiona O’Neill
Interviewed by Dibby Tyler, January 8,
2003
Fiona started by commenting that she didn’t fully
appreciate the role Ted Smith played in the design review process until he
left. Under his direction, the process was predictable with organized
procedures and consistency and clarity in responses from the DC. She had no
difficulty with the process and when she had questions, Ted gave clear and
straightforward guidance.
Since he left, Fiona has had several projects with
extremely negative comments and even some outright rejections. Some letters
expressing the DC judgments have been confusing, ambiguous and unclear.
Issues included house size and roof forms. In one case, the client wanted a
large house, purchased a lot that did not have Bane bill restrictions, and
thought he was restricted only by the 35% lot coverage rule. The first
designs were rejected as too large a house. No one would give any guidance
as to how much square footage or bulk needed to be cut. She was told it
depended on the design. She redesigned a smaller house, at considerable
expense to the client, and was told it was still too large. It took a third
design before approval was granted, by then (a one year process) the
client’s priorities had changed and the project was shelved.
In another case, the DC complained about the complexity
of the roof form. The letter included some sketches showing alternative
ways to handle the problem. The sketches all violated the site’s dominant
roof direction that she had been trying to maintain. Have the rules
changed? If so, that needs to be communicated to the design community.
The design committee membership hasn’t changed that
much, but her experience with it has changed dramatically. Ted was a strong
voice and handled communications to the owner from the DC. He may also have
had a role in keeping the DC consistent in its rulings.
When she was having no trouble with the DC, she did not
mind that meetings were not open, but now she would like the opportunity to
sit in and hear the DC members’ comments. She feels a dialog might not be
necessary; it would be helpful simply to observe.
She noted that house designs were often mundane under
Ted and commented that as an architect, she wants a smooth, predictable
process, but that as a Sea Rancher, she wants strong, different designs to
survive the process. Ted was very good at administering the process, but
may have made it too predictable to encourage innovative designs.
On the positive side, Fiona feels that the preliminary
site visits and conceptual design submittals are very good. They help
identify problems early in the design process. It sometimes helps to have
her clients hear the constraints stated by someone else.
Things seem to be settling down now with Dick Whitaker
on board. Communications from the DC are much clearer now and, as an
architect, he is available to answer questions and direct the process more
like Ted did.
Suggestions for Improvement
Fiona thinks the DC should
communicate directly with members of the design community about changes in
policy or emphasis. A letter to those designing homes at TSR would be
good. An annual meeting of all members of the DC, TSRA design staff, and
architects and designers working at Sea Ranch would be wonderful.
The design manual should be available to prospective
buyers and it should include a clear discussion of house size.
Design Committee meetings might be opened to
observation by architects and designers when their projects are being
reviewed.

APPENDIX D: FINAL TABULATION—39 INTERVIEWS WITH OWNERS ABOUT
EXPERIENCES WITH DESIGN REVIEW AT THE SEA RANCH
Conducted in November 2002
1. Unit #: 24 (8); 28 (5); 7 (3); 18 (3);
34C (3) 35E (3); 21 (2); 35F (2); 31 (2) 17 (1) 30A (1), 13 (1), 3 (1) 34A
(1), 34B (1), 35B (1), 36A (1).
2. How often do you use your Sea Ranch house?
15 - full-time
resident
2 - 6 months or more per
year
4 - 2 to 6 months per year
13 - vacations and weekends
5 - other (under
construction)
3. Is the house on a rental program?
n/a 15 (full-time owners); no 19;
yes 5
4.
Do you plan to live at Sea Ranch full-time after retirement or sometime
in the future?
Yes 12; no 9; maybe 2; n/a 15 (already full time); no answer
1
5.
How did you first learn about Sea Ranch?
Long time renter - 25
friend - 9
other - 5
6.
How much time did you spend at Sea Ranch before deciding to buy?
no answer - 1
1-2 weekends - 4
1-4 weeks - 5
more than a month - 29
7.
Before deciding to buy, did you get information from any of the
following sources:
TSR website - 3
other website(s) - 2
Sea Ranch publications - 9
ICO - 11
other books or articles -
6
TSRA office staff - 9
Sea Ranch owners - 14
realtors - 32
rental agents - 17
other sources - 13
(Gualala residents, arch./builder, work, renting, ad in newspaper, looked at
houses, son, architecture journals
8.
Reasons you might have decided to buy at Sea Ranch:
|
Reasons |
Very Important |
Important |
Somewhat Important |
Not Important |
|
location on the
coast |
3 |
34 |
0 |
2 |
|
natural
environment |
6 |
31 |
1 |
1 |
|
The Sea Ranch
concept |
9 |
19 |
6 |
5 |
|
architecture |
2 |
13 |
15 |
9 |
|
good investment
|
0 |
18 |
9 |
12 |
|
security
services |
0 |
16 |
13 |
10 |
|
roads and
utilities |
0 |
25 |
8 |
6 |
|
recreation
facilities |
1 |
14 |
10 |
14 |
|
trails |
5 |
23 |
8 |
3 |
Other reasons: wildlife, forests (2),
isolation (5), design concepts, quiet, unpopulated, beautiful (2), weather
(2), pride in place (no graffiti), views, intelligent people, commons,
community without crowds (2), abalone, close to Bay Area (3), beaches, no
traffic, social network, good for grandkids, not Gualala, cost, love it, no
Coastal Commission permit needed, TSR plan, people, ocean, Posh Squash.
9. Before you purchased your lot or house, did you
know:
septic system and leach field status no
- 5
height and bulk
limits no -
6
any Bane Bill
restrictions no - 13
design
guidelines no - 10
landscaping
restrictions no - 7
steps in the design review process no
- 14
10. Where did you get information about the design
review process at The Sea Ranch?
your realtor -
20
closing documents - 16
preliminary site visit - 13
TSRA website - 3
TSR listserve - 3
TSRA office staff - 16
architect, designer, or contractor - 30
friends - 4
other - 7 read pamphlets, inlaws, own research, TSR publications, rental
agents, magazines
11.
Did architect or designer design other Sea Ranch houses?
33 yes; 6 owner/architect
12.
Did contractor build other houses at Sea Ranch?
37 yes; 2 outside contractors
13.
What was your specific experience with design review?
DC approved initial plans with minor conditions? - 28
DC required major changes in plans? - 5
DC rejected my initial plans? - 4
Other - 1
Problems: changed house site (4); garage (3) ; roof
slope, windows (2), driveway location (2), fence (2), size, trees (2), deck
14.
Positive aspects of your experience with design review?
Architect/contractor handled it (5), clear understandable (2), plans
approved (5), reasonable expectation met, quick and easy (3) , met with
staff before submittal, predictable, Ted Smith (3), staff helpful (3), house
better than original design, flexible, Bill Wiemeyer, enjoyable, site visit
good, easy access to staff, responsive
15.
Negative aspects of your experience with design review?
Cost of septic line, too much to read, political and unfair, caught
in staff transition (2), requirements (eave width, panels on garage door,
trees removal (2), siding, screening glass blocks, overhang, courtyard size,
window type), trivial (3), arrogant gatekeeper attitude (2), staff
inflexible (4), variable office hours, house too small, staff rude,
inconsistency, trendy, took too long (4), arbitrary (2), Bane Bill limits,
rude letter rejecting plans with no specifics, too deferential to neighbors,
no reasons given for changes, last minutes changes in requirements.
16.
More info re TSR concept, design guidelines and design review
process? 33 no and 6 yes
17.
Ways to convey information about The Sea Ranch concept, design
guidelines and design review process.
|
Ways |
Very Effective |
Effective |
Somewhat Effective |
Not Effective |
Don’t Know |
|
TSR publications |
0 |
23 |
12 |
4 |
0 |
|
TSRA website |
3 |
19 |
7 |
8 |
2 |
|
contacts with
TSRA staff |
5 |
24 |
3 |
7 |
0 |
|
videotapes or
CDs |
1 |
13 |
11 |
13 |
1 |
|
meetings or
seminars |
1 |
13 |
15 |
9 |
1 |
|
displays at
specific TSR site |
1 |
13 |
13 |
12 |
0 |
Other ideas?
Guidelines organized by topic, better front desk, info for realtors and
rental agents (2), updated design manual (3), flow chart of process, summary
of process, explain tree policy, access to staff (2), seminars for
prospective owners, owner/architect participation in preliminary review, get
names of prospective buyers from realtors, brochures in rentals, reach
people before they buy, booklet with steps in process.
18.
What changes would you suggest in the design review process?
Streamline (2), summary of process, keep objective, stick to general
concepts, consistency, allow eaves, permit new materials, equal treatment,
more info about DC preferences, crack down on big houses (2), review bulk
restrictions (too severe), like advance comments on design, notify re
revised plans, adhere to original concepts, fire all staff except water
company, open up design (more like Bodega), utility yard for out-of-town
contractors, tell realtors about trees, notices are good, clarify rules for
cutting undergrowth, open DC meetings, quicker feedback, more info re Bane
Bill, higher fees and fines, no exceptions, enforce height and outdoor
lighting regulations.
19.
Any comments re experience with design review at Sea Ranch?
People need to look at houses, use a local architect, DR keeps positive
features of TSR alive, want a retreat; not a resort, don’t need an architect
to tell you where to put a plant, process helped—house better than
originally designed, Sea Ranchers are communicators and need access to
process, hold firm, keep vision intact, ombudsman needed, guidelines for
landscaping, fine if you understand and accept